    The ladder

    Day after due date Friendly first reminder, assume it is admin
    7 to 14 days later Firm second notice with a dated deadline
    No response Final demand, stating the step you will actually take
    Then Mechanics lien or small claims, whichever fits the debt

    Lien waivers, safest to most dangerous

    1. Conditional on progress payment Safest
    2. Conditional on final payment
    3. Unconditional on progress payment
    4. Unconditional on final payment Most dangerous
    The rule Conditional before the money. Unconditional only after it clears

    Before you pay a sub

    Get a W-9 Before the first payment, never in January
    No valid taxpayer ID You must withhold 24% and report it on Form 945
    1099-NEC threshold $2,000 in 2026, raised from $600
    1099-NEC deadline To the sub and the IRS by January 31

    Signed at the customer's home?

    FTC Cooling-Off Rule Applies to contracts of $25 or more signed at the customer's home
    They can cancel Within three business days, until midnight of the third business day
    Temporary sales locations Threshold is $130 or more
    State law Many states add their own right to cancel, sometimes longer
    Lien deadlines and preliminary notice requirements are set by each state, they are short, and several states require a notice early in the job or you never get lien rights at all. Check your own state clock before you rely on a lien.

    Sources: irs.gov · ftc.gov